Lena Gulch Flood Mitigation Improvements
Project Overview
Lena Gulch runs alongside US 40 (West Colfax Avenue) between I-70 and Violet Street through residential and commercial areas of Golden. Aging and undersized stormwater infrastructure has contributed to significant flooding in the area, including flooding of portions of US 40, the Golden Terrace community and nearby commercial properties. Flooding can also disrupt important emergency access routes.
The gulch has also experienced significant erosion that threatens the stability of the channel and adjacent roadway, exposes infrastructure and carries sediment downstream.
The City of Golden and Mile High Flood District began planning for improvements to Lena Gulch in 2020. That work identified a series of improvements needed to reduce flood risk, stabilize the channel and make the area more resilient during major storms.
In 2023, the City applied for and was later awarded $23.8 million in federal PROTECT Grant funding toward approximately $30 million in improvements to two sections of Lena Gulch.
Current Update – November 2026
Construction began on Reach 1 in late October 2026.
The City is working with Muller Engineering on project design and Concrete Express Inc. (CEI) as the Construction Manager/General Contractor. Federal funding for construction was released in August 2026.
Updates about construction progress, schedules and impacts will be posted on this page as the project moves forward.
What Is Being Improved?
The larger Lena Gulch improvement program includes four reaches, or sections, of the drainageway. The federally funded project will construct improvements in Reach 1 and Reach 4 while coordinating with the adjacent US 40 multimodal improvement project.
Reach 1: Martin Marietta to Heritage Square
Reach 1 extends from the south Martin Marietta access to just south of the Heritage Square entrance.
Improvements include:
Stabilizing and improving the Lena Gulch channel to reduce erosion and safely carry stormwater.
Replacing undersized drainage crossings with two new box culverts.
Creating trail underpasses at the Martin Marietta access roads so people walking and biking can travel beneath quarry traffic during normal conditions.
Improving drainage where roadway runoff currently contributes to erosion.
The trail underpasses will also carry floodwater during large storm events and may not be accessible when water levels are high.
Reach 4: Zeta Street to Violet Street
Reach 4 extends from Zeta Street to Violet Street near the Golden Terrace community.
Improvements include:
Constructing a new box culvert to increase stormwater capacity.
Improving inlet and outlet structures.
Improving how floodwater is conveyed through the area to reduce flooding along US 40 and surrounding residential and commercial properties.
Project Benefits
The Lena Gulch improvements are designed to provide several long-term benefits for the surrounding community:
Reduce flood risk along US 40 and for nearby homes and businesses.
Improve emergency access by helping keep important transportation routes passable during major storms.
Stabilize Lena Gulch and reduce erosion that threatens the roadway and other infrastructure.
Protect critical utilities located within the corridor.
Improve water quality by reducing erosion and sediment carried downstream.
Provide safer trail connections around the Martin Marietta quarry access roads.
Reduce downstream flood impacts by improving how stormwater moves through the Lena Gulch system.
Support a healthier stream corridor through channel stabilization and other nature-based improvements.
Project Funding
The estimated cost for the Reach 1 and Reach 4 improvements is approximately $30 million.
In 2023, the City successfully applied for $23.8 million through the Federal Highway Administration’s Promoting Resilient Operations for Transformative, Efficient, and Cost-Saving Transportation (PROTECT) Program. The program provides federal funding for transportation infrastructure improvements that increase resilience to flooding and other natural hazards.
In addition, the Golden Urban Renewal Authority (GURA) has contributed $200,000 to the project in support of its benefits to businesses and redevelopment opportunities.
The City is completing the project in partnership with the Mile High Flood District and coordinating closely with the Colorado Department of Transportation (CDOT) because US 40 is a state highway.
Project Timeline
2020: City and Mile High Flood District begin planning for improvements to Lena Gulch.
2023: City applies for federal PROTECT Grant funding for Reach 1 and Reach 4.
September 2025: Federal funding agreement executed, allowing design and environmental clearance work to proceed.
September 2025: City contracts with Muller Engineering for project design.
January 2026: City contracts with Concrete Express Inc. as Construction Manager/General Contractor.
August 2026: Federal agreement amended to release construction funding.
Late October 2026: Construction begins on Reach 1.